Improve base on 8 North from CR3 east to the County Line Road (3 mi)
-
Improve base on the 2 east from Hwy 160 to the 1 South (.5 mi)
-
Improve base on the 1 South from 1 West to the 2 West (1 mi)
-
Pave Approximately .6 mi on Escondida Drive (Taxing project)
-
Complete the overlay project on the 2 east from the 7 North to the 10.5 North (Impact Fee Use)
-
CR 15 base work from Alder to Bear Creek(Impact Fee Use)
-
Skin patch and Chip Seal as funds allow
-
Place field rock on the 11 south from the 4 to the 5 East
-
Possible joint project with X-Cel energy to bury high pressure gas line on 1 south
-
Clean and repair culverts on Cat Creek and Rock Creek Roads
-
Replace bridge on 2 East and 4.5 North